Jamnagar/Kalvad 1

Jamnagar/Kalvad 1 - 170.0 MW Wind Solar Hybrid Project
Capacity 170.0 MW Wind Solar Hybrid Project
Location Jamnagar, Gujarat
Status Under Construction
WTGs 24 X Senvion M130 2.7 MW
Credit Rating
Solar Modules 93.0 MWp - Warree and balance TBD
Additional details
  • 33 / 220 kV pooling substation completed; charging expected shortly
  • All 77/77 towers of 220 kV double circuit transmission line (~23.0 km) to 220 / 400 kV Kalvad substation of GETCO erected
  • Delivery of WTGs have commenced at the project site. 13 WTGs already delivered at site and 12 WTGs installed.
  • Module equivalent to 93.0 MWp already delivered.
  • Financial closure and debt drawdown achieved with Power Finance Corporation
  • PPAs with Commercial & Industrial Consumers within the state of Gujarat