Ratlam - 2

Ratlam - 2 - 250.0 MW Wind-Solar Hybrid Project
Capacity 250.0 MW Wind-Solar Hybrid Project
Location Ratlam & Mandsaur Districts, Madhya Pradesh
Status Under construction
WTGs 37 x GE132-2.7 MW
Credit Rating
Solar Modules 150.1 MWp - Waaree, Premier
Additional details
  • Brownfield expansion at our existing Ratlam – 1
    • 33 / 220 kV 300 MVA pooling substation operational
    • 220 kV transmission line of ~20.0 km is operational (conductor capacity enhanced by hotline reconductoring)
  • 100% of WTGs installed at site and 35 WTGs are commissioned
  • All 150.1 MWp solar modules are delivered and under installation at the project site / warehouse. Successfully commissioned 35.0 MWp out of 150.0 MWp
  • Financial closure and debt drawdown achieved with Indian Renewable Energy Development Agency
  • PPAs with Commercial & Industrial Consumers within the state of Madhya Pradesh